Dept. of Trans. PROGRESS Serial No. Contract No. 07-298-07-27 05-452604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 34% 05-SLO-41-49.7/50.4 Federal Project: 05-KER-41-0.0/1.2 NONE Progress payment No. 03 Payment period ending: 10-20-07 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 789,762.15 329,014.00 2.a. Extra Work 28,908.20 28,908.20 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 818,670.35 357,922.20 5. Mobilization 95,000.00 20,000.00 6. Total Work Completed 913,670.35 7. Deductions -5,800.00 0.00 8. a.Contract Retentions -66,229.17 -20,154.35 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 841,641.18 357,767.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 357,767.85