Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-25 05-452604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 05-SLO-41-49.7/50.4 Federal Project: 05-KER-41-0.0/1.2 NONE Progress payment No. 11 Payment period ending: 06-20-08 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,055,039.91 252,978.05 2.a. Extra Work 126,165.01 0.00 b. Adjustment Comp. 62,015.23 -27,300.00 3. Materials on Hand 4. Earned Subject to Retention 3,243,220.15 225,678.05 5. Mobilization 100,000.00 0.00 6. Total Work Completed 3,343,220.15 7. Deductions -16,300.00 0.00 8. a.Contract Retentions -162,161.01 -11,283.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,164,759.14 214,394.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,394.15