Dept. of Trans. PROGRESS Serial No. Contract No. 01-110-10-03 05-4610U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 91% 05-SB-246-26.1/ .0 Federal Project: ACST-P246(14) P-P246(14) STPE-P246(14) Progress payment No. 06 Payment period ending: 04-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,074,885.49 318,430.37 2.a. Extra Work 16,813.47 7,174.83 b. Adjustment Comp. -487.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,091,211.96 325,605.20 5. Mobilization 6. Total Work Completed 1,091,211.96 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -54,560.60 -16,280.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,016,651.36 309,324.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 309,324.94