Dept. of Trans. PROGRESS Serial No. Contract No. 01-295-13-39 05-4610U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SB-246-26.1/ .0 Federal Project: ACST-P246(14) P-P246(14) STPE-P246(14) Progress payment No. 11 Payment period ending: 10-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,098,353.74 480.00 2.a. Extra Work 51,523.59 0.00 b. Adjustment Comp. -487.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,149,390.33 480.00 5. Mobilization 6. Total Work Completed 1,149,390.33 7. Deductions -22,600.00 0.00 8. a.Contract Retentions -57,469.52 -24.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,069,320.81 456.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456.00