Dept. of Trans. PROGRESS Serial No. Contract No. 03-233-13-07 05-461604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 05-SLO-1-28.5/32.0 Federal Project: 05-SLO-101-14.6/30.2 ACST-X079(29) P-X079(29) Progress payment No. 13 Payment period ending: 08-20-03 TIFFANY GROUP INC 19528 VENTURA BLVD STE 359 TARZANA CA 91356 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 671,209.95 64,529.95 2.a. Extra Work 88,512.19 2,762.22 b. Adjustment Comp. 3,671.18 -1,995.00 3. Materials on Hand 4. Earned Subject to Retention 763,393.32 65,297.17 5. Mobilization 80,000.00 0.00 6. Total Work Completed 843,393.32 7. Deductions -27,052.33 -15,000.00 8. a.Contract Retentions -38,169.67 -3,264.86 b. Unsatisfactory Prog. -6,239.55 -3,264.86 c. Reduction after 95% Comp. 9. Total pay to Contractor 771,931.77 43,767.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,767.45