Dept. of Trans. PROGRESS Serial No. Contract No. 03-113-14-07 05-462104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 8% 05-SB-101-12.7/19.8 Federal Project: ACNH-Q101(13) Progress payment No. 04 Payment period ending: 04-20-03 AMERICA WEST LANDSCAPE INC P O BOX 1698 BELLFLOWER CA 90707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 254,238.78 66,229.76 2.a. Extra Work 9,568.84 9,568.84 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 263,807.62 75,798.60 5. Mobilization 42,077.64 8,858.45 6. Total Work Completed 305,885.26 7. Deductions 8. a.Contract Retentions -21,362.71 -2,561.81 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 284,522.55 82,095.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,095.24