Dept. of Trans. PROGRESS Serial No. Contract No. 14-167-13-58 05-4625A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 05-SB-101-0.3/7.5 Federal Project: NONE Progress payment No. 11 Payment period ending: 06-20-14 SPIESS CONSTRUCTION CO., INC PO BOX 2849 SANTA MARIA, CA 93457 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 116,294.40 5,947.20 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 116,294.40 5,947.20 5. Mobilization 6. Total Work Completed 116,294.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 116,294.40 5,947.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,947.20