Dept. of Trans. PROGRESS Serial No. Contract No. 04-170-08-02 05-465604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 29% 05-SCR-9-9.4/9.7 Federal Project: ACST-S009(13) PH-S009(13) Progress payment No. 03 Payment period ending: 06-20-04 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST ST REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 428,201.10 207,753.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 428,201.10 207,753.90 5. Mobilization 90,250.00 19,000.00 6. Total Work Completed 518,451.10 7. Deductions 8. a.Contract Retentions -26,541.91 -4,497.19 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 491,909.19 222,256.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,256.71