Dept. of Trans. PROGRESS Serial No. Contract No. 04-237-08-12 05-465604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 46% 05-SCR-9-9.4/9.7 Federal Project: ACST-S009(13) PH-S009(13) Progress payment No. 05 Payment period ending: 08-20-04 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST ST REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 695,254.67 14,860.00 2.a. Extra Work 22,144.25 12,613.41 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 717,398.92 27,473.41 5. Mobilization 95,000.00 0.00 6. Total Work Completed 812,398.92 7. Deductions -5,000.00 5,000.00 8. a.Contract Retentions -35,869.95 -1,373.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 771,528.97 31,099.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,099.74