Dept. of Trans. PROGRESS Serial No. Contract No. 05-299-08-29 05-465604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SCR-9-9.4/9.7 Federal Project: ACST-S009(13) PH-S009(13) Progress payment No. 19 Payment period ending: 10-20-05 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST ST REDWOOD CITY CA 94063 Escrow No. 02174 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,253,167.69 1,260.00 2.a. Extra Work 121,399.18 0.00 b. Adjustment Comp. 24,468.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,399,035.77 1,260.00 5. Mobilization 95,000.00 0.00 6. Total Work Completed 1,494,035.77 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -69,951.79 -63.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,423,083.98 1,197.00 10. Reduction Amt to Escrow 11. Payment to Escrow 69,950.00 12. Net Pymt. this Estimate 1,197.00