Dept. of Trans. PROGRESS Serial No. Contract No. 02-141-13-08 05-466104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 77% 05-SLO-101-55.5/56.0 Federal Project: NONE Progress payment No. 08 Payment period ending: 05-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 482,418.87 263,289.09 2.a. Extra Work 21,692.99 3,838.27 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 504,111.86 267,127.36 5. Mobilization 6. Total Work Completed 504,111.86 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -25,205.59 -13,356.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 477,906.27 253,771.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 253,771.00