Dept. of Trans. PROGRESS Serial No. Contract No. 06-143-11-27 05-4757V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 50% 05-MON-1-74.9/R80.8 Federal Project: ACST-P001(500) PH-P001(500) Progress payment No. 22 Payment period ending: 05-20-06 J S BRAR COMPANY 2779 BULLARD AVE CLOVIS CA 936113414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 762,433.88 3,470.75 2.a. Extra Work 6,665.04 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 769,098.92 3,470.75 5. Mobilization 42,900.00 0.00 6. Total Work Completed 811,998.92 7. Deductions -4,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 807,998.92 3,470.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,470.75