Dept. of Trans. PROGRESS Serial No. Contract No. 10-236-15-03 05-485624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-101-13.2/18.3 Federal Project: NONE Progress payment No. 20 Payment period ending: 08-20-10 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02409 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,629,783.79 2,220.00 2.a. Extra Work 424,814.03 63,288.50 b. Adjustment Comp. 555,777.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,610,375.44 65,508.50 5. Mobilization 553,000.00 0.00 6. Total Work Completed 6,163,375.44 7. Deductions -71,000.00 1,000.00 8. a.Contract Retentions -280,518.77 -3,275.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,811,856.67 63,233.08 10. Reduction Amt to Escrow 11. Payment to Escrow 280,510.00 12. Net Pymt. this Estimate 63,233.08