Dept. of Trans. PROGRESS Serial No. Contract No. 10-323-14-25 05-485624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-101-13.2/18.3 Federal Project: NONE Progress payment No. 23 Payment period ending: 11-20-10 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02409 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,737,653.49 54,276.90 2.a. Extra Work 452,092.91 0.00 b. Adjustment Comp. 538,347.82 -20,259.30 3. Materials on Hand 4. Earned Subject to Retention 5,728,094.22 34,017.60 5. Mobilization 553,000.00 0.00 6. Total Work Completed 6,281,094.22 7. Deductions -71,000.00 1,000.00 8. a.Contract Retentions -286,404.71 -1,700.88 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,923,689.51 33,316.72 10. Reduction Amt to Escrow 11. Payment to Escrow 286,400.00 12. Net Pymt. this Estimate 33,316.72