Dept. of Trans. PROGRESS Serial No. Contract No. 16-026-13-47 05-492804 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 11% Location: Federal Project: 05-SLO-1-64.0/R66.9 STP-P001(590) Progress payment No. 004 Payment period ending: 01-20-16 PAPICH CONSTRUCTION CO. INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 646,070.09 16,333.25 2. a. Extra Work 4,765.38 0.00 b. Adustment Comp. 3. Materials on Hand 541,018.75 0.00 4. Earned Subject to Retention 1,191,854.22 16,333.25 5. Mobilization 775,000.00 0.00 6. Total Work Completed 1,425,835.47 7. Deductions -47,007.77 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,919,846.45 16,333.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,333.25