Dept. of Trans. PROGRESS Serial No. Contract No. 17-053-15-05 05-492804 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 37% Location: Federal Project: 05-SLO-1-64.0/R66.9 STP-P001(590) Progress payment No. 017 Payment period ending: 02-20-17 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,926,041.49 642,423.60 2. a. Extra Work 402,746.26 133,604.50 b. Adustment Comp. 61,426.55 30,500.00 3. Materials on Hand 4. Earned Subject to Retention 12,390,214.30 806,528.10 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 13,940,214.30 7. Deductions -17,746.32 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,922,467.98 806,528.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 806,528.10