Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-13-35 05-492804 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 47% Location: Federal Project: 05-SLO-1-64.0/R66.9 STP-P001(590) Progress payment No. 021 Payment period ending: 06-20-17 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,325,358.41 1,100,010.60 2. a. Extra Work 1,205,062.85 47,418.29 b. Adustment Comp. 61,426.55 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,591,847.81 1,147,428.89 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 17,141,847.81 7. Deductions -17,746.32 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,124,101.49 1,147,428.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,147,428.89