Dept. of Trans. PROGRESS Serial No. Contract No. 18-263-13-24 05-492824 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 19% Location: Federal Project: 05-SLO-1-64.0/R66.9 ACST-S001(638) Progress payment No. 002 Payment period ending: 09-20-18 EMPIRE LANDSCAPING INC PO BOX 35 DAVIS CA 95617-0035 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 180,594.00 107,684.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 180,594.00 107,684.00 5. Mobilization 100,000.00 100,000.00 6. Total Work Completed 280,594.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 280,594.00 207,684.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,684.00