Dept. of Trans. PROGRESS Serial No. Contract No. 19-109-12-22 05-492824 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 67% Location: Federal Project: 05-SLO-1-64.0/R66.9 ACST-S001(638) Progress payment No. 009 Payment period ending: 04-20-19 EMPIRE LANDSCAPING INC PO BOX 35 DAVIS CA 95617-0035 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,077,711.95 16,800.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,077,711.95 16,800.00 5. Mobilization 200,000.00 0.00 6. Total Work Completed 1,277,711.95 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,266,711.95 16,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,800.00