Dept. of Trans. PROGRESS Serial No. Contract No. 08-205-10-14 05-496804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 31% 05-SCR-129-7.9/8.2 Federal Project: ACST-P129(14) PH-P129(14) Progress payment No. 03 Payment period ending: 07-20-08 PROVEN MANAGEMENT INC 706 SANSOME STREET SAN FRANCISCO CA 94111 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 429,239.72 296,274.81 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 214,224.37 214,224.37 4. Earned Subject to Retention 643,464.09 510,499.18 5. Mobilization 47,500.00 22,500.00 6. Total Work Completed 476,739.72 7. Deductions -1,650.00 -825.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 689,314.09 532,174.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 532,174.18