Dept. of Trans. PROGRESS Serial No. Contract No. 08-296-12-58 06-0A4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 33% 06-MAD-41-19.8/20.1 Federal Project: ACST-P041(106) PHG-P041(106) CMNL-5941(48) Progress payment No. 02 Payment period ending: 10-20-08 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,904.00 163,445.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 166,904.00 163,445.00 5. Mobilization 81,711.75 81,711.75 6. Total Work Completed 248,615.75 7. Deductions -1,484.70 -1,484.70 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 247,131.05 243,672.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 243,672.05