Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-06-37 06-0A5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 37% 06-KER-58-R55.7/56.6 Federal Project: ACST-P058(102) PE-P058(102) Progress payment No. 02 Payment period ending: 10-20-06 A C C U CONSTRUCTION P O BOX 23135 PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 300,806.50 233,883.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 300,806.50 233,883.00 5. Mobilization 95,000.00 45,000.00 6. Total Work Completed 395,806.50 7. Deductions -5,214.64 -2,470.09 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 390,591.86 276,412.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,412.91