Dept. of Trans. PROGRESS Serial No. Contract No. 07-053-07-07 06-0A5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 62% 06-KER-58-R55.7/56.6 Federal Project: ACST-P058(102) PE-P058(102) Progress payment No. 06 Payment period ending: 02-20-07 A C C U CONSTRUCTION 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 603,889.50 109,482.00 2.a. Extra Work 18,882.81 3,053.94 b. Adjustment Comp. 3. Materials on Hand 0.00 -30,921.33 4. Earned Subject to Retention 622,772.31 81,614.61 5. Mobilization 100,000.00 0.00 6. Total Work Completed 722,772.31 7. Deductions -5,489.10 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 717,283.21 81,614.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,614.61