Dept. of Trans. PROGRESS Serial No. Contract No. 09-356-06-04 06-0A7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 29% 06-KER-99-28.2/29.0 Federal Project: ACST-P099(516) PE-P099(516) Progress payment No. 11 Payment period ending: 12-20-09 ODYSSEY LANDSCAPING COMPANY INC 5400 W HIGHWAY 12 LODI CA 95242 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 244,604.97 917.22 2.a. Extra Work 32,795.67 1,757.60 b. Adjustment Comp. -8,864.72 0.00 3. Materials on Hand 4. Earned Subject to Retention 268,535.92 2,674.82 5. Mobilization 17,084.00 0.00 6. Total Work Completed 285,619.92 7. Deductions -78.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 285,541.92 2,674.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,674.82