Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-05-43 06-0A7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 46% 06-KER-99-28.2/29.0 Federal Project: ACST-P099(516) PE-P099(516) Progress payment No. 18 Payment period ending: 07-20-10 ODYSSEY LANDSCAPING COMPANY INC 5400 W HIGHWAY 12 LODI CA 95242 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 251,112.84 917.22 2.a. Extra Work 32,795.67 0.00 b. Adjustment Comp. -8,864.72 0.00 3. Materials on Hand 4. Earned Subject to Retention 275,043.79 917.22 5. Mobilization 17,084.00 0.00 6. Total Work Completed 292,127.79 7. Deductions -78.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 292,049.79 917.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 917.22