Dept. of Trans. PROGRESS Serial No. Contract No. 11-024-07-39 06-0A7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 61% 06-KER-99-28.2/29.0 Federal Project: ACST-P099(516) PE-P099(516) Progress payment No. 24 Payment period ending: 01-20-11 ODYSSEY LANDSCAPING COMPANY INC 5400 W HIGHWAY 12 LODI CA 95242 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 256,703.50 917.22 2.a. Extra Work 32,795.67 0.00 b. Adjustment Comp. -8,864.72 0.00 3. Materials on Hand 4. Earned Subject to Retention 280,634.45 917.22 5. Mobilization 17,084.00 0.00 6. Total Work Completed 297,718.45 7. Deductions -78.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 297,640.45 917.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 917.22