Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-200-13-50 06-0A8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-99-L0.7/2.7 Federal Project: ACST-P099(508) PHG-P099(508) Progress payment No. 05 Payment period ending: 06-28-07 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,477,501.21 -81,793.80 2.a. Extra Work 13,108.79 13,108.79 b. Adjustment Comp. 22.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,490,632.71 -68,685.01 5. Mobilization 151,350.00 0.00 6. Total Work Completed 1,641,982.71 7. Deductions 0.00 22,410.49 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,641,982.71 -46,274.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -46,274.52