Dept. of Trans. PROGRESS Serial No. Contract No. 11-111-07-36 06-0A9904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 15% 06-KER-5-0.8/ .0 Federal Project: ACHS-005-4(183) IMG-005-4(183) Progress payment No. 04 Payment period ending: 04-20-11 J T S CONSTRUCTION P.O. BOX 41765 BAKERSFIELD, CA 93384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 554,764.40 172,817.74 2.a. Extra Work 19,894.45 19,069.44 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 574,658.85 191,887.18 5. Mobilization 6. Total Work Completed 574,658.85 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 574,658.85 191,887.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 191,887.18