Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-319-07-16 06-0C3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-33-61.2/62.3 Federal Project: 06-FRE-180-23.5/24.6 NONE 06-FRE-180-42.4/53.7 Progress payment No. 04 Payment period ending: 07-08-05 VALLEY SLURRY SEAL COMPANY P O BOX 981330 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 540,730.43 0.00 2.a. Extra Work 11,718.10 5,584.89 b. Adjustment Comp. 3,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 555,948.53 5,584.89 5. Mobilization 6. Total Work Completed 555,948.53 7. Deductions -500.00 22,014.80 8. a.Contract Retentions -26,029.12 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 26,029.12 0.00 9. Total pay to Contractor 555,448.53 27,599.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,599.69