Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-077-06-14 06-0C5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-41-R22.5/R26.5 Federal Project: 06-FRE-180-R58.6/ .0 NONE Progress payment No. 05 Payment period ending: 10-31-08 PROFESSIONAL CONSTRUCTION SERVICES 3309 VINCENT ROAD PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 520,832.81 7,695.00 2.a. Extra Work 16,930.95 16,930.95 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 537,763.76 24,625.95 5. Mobilization 14,000.00 0.00 6. Total Work Completed 551,763.76 7. Deductions -19,900.00 10,000.00 8. a.Contract Retentions -24,100.92 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 24,100.92 0.00 9. Total pay to Contractor 531,863.76 34,625.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,625.95