Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-06-29 06-0C5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 94% 06-KER-178-100.6/104.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-06 ASPHALT CONSTRUCTION CO INC P O BOX 1187 LANCASTER CA 93584 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 803,312.72 803,312.72 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 803,312.72 803,312.72 5. Mobilization 6. Total Work Completed 803,312.72 7. Deductions 8. a.Contract Retentions -40,165.64 -40,165.64 b. Unsatisfactory Prog. -40,165.63 -40,165.63 c. Reduction after 95% Comp. 9. Total pay to Contractor 722,981.45 722,981.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 722,981.45