Dept. of Trans. PROGRESS Serial No. Contract No. 06-206-06-39 06-0C6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 85% 06-MAD-99-19.6/22.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-06 DIVERSIFIED CONCRETE CUTTING INC 59 CONEY ISLAND DRIVE SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,633.25 287,270.95 2.a. Extra Work 174,059.42 34,664.97 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 502,692.67 321,935.92 5. Mobilization 6. Total Work Completed 502,692.67 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -25,134.63 -16,096.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 467,558.04 295,839.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 295,839.13