Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-09-42 06-0E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 34% 06-MAD-99-9.5/13.1 Federal Project: NH-P099(538) Progress payment No. 09 Payment period ending: 06-20-12 GRANITE CONSTRUCTION COMPANY ATTN JEFF GRIMM P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,164,715.10 812,929.46 2.a. Extra Work 1,000,977.51 0.00 b. Adjustment Comp. -9,865.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,155,827.59 812,929.46 5. Mobilization 6. Total Work Completed 7,155,827.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,155,827.59 812,929.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 812,929.46