Dept. of Trans. PROGRESS Serial No. Contract No. 13-142-09-19 06-0E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 81% 06-MAD-99-9.5/13.1 Federal Project: NH-P099(538) Progress payment No. 21 Payment period ending: 05-20-13 GRANITE CONSTRUCTION COMPANY ATTN JEFF GRIMM P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,313,494.31 1,400,045.18 2.a. Extra Work 3,912,527.54 0.00 b. Adjustment Comp. -9,865.02 0.00 3. Materials on Hand 0.00 -276,719.62 4. Earned Subject to Retention 22,216,156.83 1,123,325.56 5. Mobilization 6. Total Work Completed 22,216,156.83 7. Deductions -194,516.75 -194,250.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,021,640.08 929,075.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 929,075.56