Dept. of Trans. PROGRESS Serial No. Contract No. 13-168-13-07 06-0E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 89% 06-MAD-99-9.5/13.1 Federal Project: NH-P099(538) Progress payment No. 22 Payment period ending: 06-20-13 GRANITE CONSTRUCTION COMPANY ATTN JEFF GRIMM P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,600,632.63 1,287,138.32 2.a. Extra Work 3,912,527.54 0.00 b. Adjustment Comp. -9,865.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 23,503,295.15 1,287,138.32 5. Mobilization 6. Total Work Completed 23,503,295.15 7. Deductions -194,516.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,308,778.40 1,287,138.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,287,138.32