Dept. of Trans. PROGRESS Serial No. Contract No. 13-326-05-13 06-0E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 06-MAD-99-9.5/13.1 Federal Project: NH-P099(538) Progress payment No. 27 Payment period ending: 11-20-13 GRANITE CONSTRUCTION COMPANY ATTN JEFF GRIMM P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,174,909.27 22,581.38 2.a. Extra Work 5,268,061.69 13,519.49 b. Adjustment Comp. -9,865.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 27,433,105.94 36,100.87 5. Mobilization 6. Total Work Completed 27,433,105.94 7. Deductions -194,673.75 -157.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,238,432.19 35,943.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,943.87