Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-07-34 06-0E3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 61% 06-FRE-41-R21.0/R29.3 Federal Project: NONE Progress payment No. 05 Payment period ending: 01-20-12 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,337,524.91 -98,015.21 2.a. Extra Work 201,255.83 159,315.56 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,538,780.74 61,300.35 5. Mobilization 59,433.50 0.00 6. Total Work Completed 1,598,214.24 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,588,214.24 51,300.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,300.35