Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-173-06-36 06-0E3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-41-R21.0/R29.3 Federal Project: NONE Progress payment No. 08 Payment period ending: 06-07-12 DREAMBUILDER 1324 LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,595,362.40 26,715.91 2.a. Extra Work 250,255.83 49,000.00 b. Adjustment Comp. -8,306.03 -8,306.03 3. Materials on Hand 4. Earned Subject to Retention 1,837,312.20 67,409.88 5. Mobilization 59,433.50 0.00 6. Total Work Completed 1,896,745.70 7. Deductions -12,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,884,745.70 67,409.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,409.88