Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-192-07-09 06-0E3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-41-R21.0/R29.3 Federal Project: NONE Progress payment No. 09 Payment period ending: 06-07-12 DREAMBUILDER 1324 LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,565,797.40 -29,565.00 2.a. Extra Work 250,255.83 0.00 b. Adjustment Comp. -8,306.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,807,747.20 -29,565.00 5. Mobilization 59,433.50 0.00 6. Total Work Completed 1,867,180.70 7. Deductions -12,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,855,180.70 -29,565.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -29,565.00