Dept. of Trans. FINAL Serial No. Contract No. 12-285-05-17 06-0E3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-41-R21.0/R29.3 Federal Project: NONE Progress payment No. 10 Payment period ending: 06-07-12 DREAMBUILDER 1324 LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,565,797.40 0.00 2.a. Extra Work 271,218.38 20,962.55 b. Adjustment Comp. -8,306.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,828,709.75 20,962.55 5. Mobilization 59,433.50 0.00 6. Total Work Completed 1,888,143.25 7. Deductions 0.00 12,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,888,143.25 32,962.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,962.55