Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-027-09-57 06-0E4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-119-29.3/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-14-09 VICTORY ENGINEERS INC 575 E ALLUVIAL AVE NO 106 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 505,522.50 55,021.25 2.a. Extra Work 17,432.61 4,652.23 b. Adjustment Comp. 10,000.00 10,000.00 3. Materials on Hand 4. Earned Subject to Retention 532,955.11 69,673.48 5. Mobilization 6. Total Work Completed 532,955.11 7. Deductions -5,502.12 -5,502.12 8. a.Contract Retentions -23,164.08 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 23,164.08 23,164.08 9. Total pay to Contractor 527,452.99 87,335.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,335.44