Dept. of Trans. PROGRESS Serial No. Contract No. 07-358-05-21 06-0E6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 95% 06-KER-58-R55.2/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 12-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 604,077.01 50,550.88 2.a. Extra Work 838.30 0.00 b. Adjustment Comp. 3,516.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 608,431.31 50,550.88 5. Mobilization 40,000.00 0.00 6. Total Work Completed 648,431.31 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions -30,421.57 -2,527.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 613,009.74 43,023.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,023.33