Dept. of Trans. PROGRESS Serial No. Contract No. 07-268-05-53 06-0F1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 76% 06-TUL-99-6.1/7.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-07 D C HUBBS CONSTRUCTION 37306 VISTA VIEW DR YUCAIPA CA 92399 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 111,564.68 99,708.68 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 111,564.68 99,708.68 5. Mobilization 6. Total Work Completed 111,564.68 7. Deductions 8. a.Contract Retentions -7,677.76 -6,492.16 b. Unsatisfactory Prog. -3,478.71 -3,478.71 c. Reduction after 95% Comp. 9. Total pay to Contractor 100,408.21 89,737.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,737.81