Dept. of Trans. PROGRESS Serial No. Contract No. 07-205-13-06 06-0F4204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 17% 06-FRE-145-35.2/41.2 Federal Project: 06-FRE-168-18.6/25.5 NONE 06-FRE-180-66.0/71.6 Progress payment No. 01 Payment period ending: 07-20-07 LEES PAVING INC 1212 N PLAZA DRIVE VISALIA CA 93291 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 332,530.00 332,530.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 332,530.00 332,530.00 5. Mobilization 6. Total Work Completed 332,530.00 7. Deductions 8. a.Contract Retentions -33,253.00 -33,253.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 299,277.00 299,277.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 299,277.00