Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-007-07-22 06-0F5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-178-97.0/98.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-19-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 321,480.79 0.00 2.a. Extra Work b. Adjustment Comp. -18,045.35 0.00 3. Materials on Hand 4. Earned Subject to Retention 303,435.44 0.00 5. Mobilization 6. Total Work Completed 303,435.44 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -15,171.77 0.00 b. Unsatisfactory Prog. 0.00 11,024.79 c. Reduction after 95% Comp. 15,171.77 15,171.77 9. Total pay to Contractor 293,435.44 36,196.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,196.56