Dept. of Trans. FINAL Serial No. Contract No. 09-098-06-26 06-0F5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-178-97.0/98.0 Federal Project: NONE Progress payment No. 05 Payment period ending: 12-19-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 323,082.09 0.00 2.a. Extra Work 1,136.54 0.00 b. Adjustment Comp. -16,811.98 1,233.37 3. Materials on Hand 4. Earned Subject to Retention 307,406.65 1,233.37 5. Mobilization 6. Total Work Completed 307,406.65 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -15,171.77 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 15,171.77 0.00 9. Total pay to Contractor 307,406.65 11,233.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,233.37