Dept. of Trans. FINAL Serial No. Contract No. 08-344-13-36 06-0F8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-33-36.6/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 08-20-08 BUGLER CONSTRUCTION 47000 WARM SPRINGS BLVD #101 FREMONT CA 94539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 295,800.66 0.00 2.a. Extra Work b. Adjustment Comp. 14,300.00 14,300.00 3. Materials on Hand 4. Earned Subject to Retention 310,100.66 14,300.00 5. Mobilization 6. Total Work Completed 310,100.66 7. Deductions 0.00 20,000.00 8. a.Contract Retentions -14,782.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 14,782.53 0.00 9. Total pay to Contractor 310,100.66 34,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,300.00