Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-06-37 06-0G0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 100% 06-KIN-41-15.5/20.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-06 GARCIA PAVING COMPANY INC 2951 S ELM FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 462,924.40 462,924.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 462,924.40 462,924.40 5. Mobilization 6. Total Work Completed 462,924.40 7. Deductions -15,000.00 -15,000.00 8. a.Contract Retentions -23,146.22 -23,146.22 b. Unsatisfactory Prog. -23,146.22 -23,146.22 c. Reduction after 95% Comp. 9. Total pay to Contractor 401,631.96 401,631.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 401,631.96