Dept. of Trans. FINAL Serial No. Contract No. 07-030-05-18 06-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KIN-198-7.2/9.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-16-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 511,582.51 0.00 2.a. Extra Work 5,048.50 2,875.00 b. Adjustment Comp. -3,408.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 513,222.99 2,875.00 5. Mobilization 6. Total Work Completed 513,222.99 7. Deductions 0.00 7,788.21 8. a.Contract Retentions -21,685.02 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 21,685.02 0.00 9. Total pay to Contractor 513,222.99 10,663.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,663.21