Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-06-58 06-0G2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 93% 06-KER-99-21.6/24.7 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-20-08 ODYSSEY LANDSCAPING COMPANY INC 800 WEST EIGHT MILE ROAD STOCKTON CA 95209 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,565.20 69,498.71 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 193,565.20 69,498.71 5. Mobilization 34,890.13 0.00 6. Total Work Completed 228,455.33 7. Deductions 8. a.Contract Retentions -9,689.38 0.00 b. Unsatisfactory Prog. -6,192.21 -3,474.94 c. Reduction after 95% Comp. 9. Total pay to Contractor 212,573.74 66,023.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,023.77